I have a manufactured part I only want to build when I have actual demand, not to forecast. I would use a planning method of next level demand, however, there are very long lead times for the purchased raw material to build the component and I would like the Finished Good forecast to drive requirements for the purchased material.
Consider this example…
Finished Good – Bike
Manufactured Component – Wheel
Purchased – Tire
I want to purchase enough tires to support the Finished good demand. However, I don’t want to assemble the wheels unless there is actual demand for the bike. Reason being there is a very long lead time on tires and a very high cost of assembling wheels.
Is it possible to not have MRP generate requisitions for the component or finished good, but still generate purchase reqs for raw materials? Is it possible to accomplish this, and still have the make parts included in CRP?