Question

MRB Case - Checklist and approval process

  • 3 May 2023
  • 1 reply
  • 149 views

Userlevel 1
Badge +5
  • Sidekick (Partner)
  • 13 replies

Customer has a business requirement to make it mandatory for the user to add a checklist/approval process before completion of both MRB line and MRB case. Is there a standard basic data parameter to define this behavior ?

 

Like your feedback and thoughts on the above.

 

Thanks and Regards,

Edie


1 reply

Userlevel 6
Badge +17

Hi @Edie ,

We do have a checklist function available in MRB. You can define the default check list for site & non conformance in MRB basic date and this checklist will be automatically fetched when a new MRB is created. You cannot close the MRB case until all the check list lines are approved.

Note: if the non conformance is empty then the checklist will applicable for all the non conformances 

 

Hope this helps!!

Regards,

Mithun K V

Reply