Lead time calculation and calendar exceptions

  • 22 November 2023
  • 1 reply
  • 99 views

Forum|alt.badge.img+10

We are using IFS 10 UPD 9,  we have a scheduled job to daily run Manufacturing Lead Time Calculation.  We are finding that it is very consistent from day to day unless the job runs on a day that is a calendar exception.  If it runs on the exception day, it is increasing the lead time on parts by 1-25 days.

Can anyone explain why this is happening and if there is a way to prevent this?

Best answer by Björn Hultgren

The reason is probably the highlighted part below. How to prevent? Avoid performing the calculation on days when you have schedule exceptions. 

 

View original

Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+23

The reason is probably the highlighted part below. How to prevent? Avoid performing the calculation on days when you have schedule exceptions. 

 


Reply