Lead time calculation and calendar exceptions

  • 22 November 2023
  • 1 reply
  • 57 views

Userlevel 5
Badge +9

We are using IFS 10 UPD 9,  we have a scheduled job to daily run Manufacturing Lead Time Calculation.  We are finding that it is very consistent from day to day unless the job runs on a day that is a calendar exception.  If it runs on the exception day, it is increasing the lead time on parts by 1-25 days.

Can anyone explain why this is happening and if there is a way to prevent this?

icon

Best answer by Björn Hultgren 23 November 2023, 09:35

View original

1 reply

Userlevel 7
Badge +23

The reason is probably the highlighted part below. How to prevent? Avoid performing the calculation on days when you have schedule exceptions. 

 