hi,
yes, actually it was in apps10 that some new things were done for DOPs. so it would be different in app8.
this is the list of the changes in APP10:
- Move reserved material was introduced and that affects DOP
- Possibility to on site level control if and what type of reserved lines that should be allowed to move in inventory
- Possible to move a part from one location to another, even if there are material reservations for the part on the location to move from
Implemented in DOP for
- DOP Temp Inventory Reservations
- DOP Inventory Reservations
- Redesign DOP Supply Connection
- Possibility to easily review the remaining quantity a supply order is expected to supply a DOP order with
- Scrap and substitute receipt costs from a shop order supplying multiple DOP orders will be distributed to the DOP orders based on the actual quantity delivered to the DOP order
- Parent DOP Quantity Alarms are generated when the quantity required of a DOP supplied shop order material line changes as a result component scrapping or manual changes
- DOP and interim order structure and supply orders are generated considering the scrap factor of the inventory part allowing:
- DOP and interim order costs now includes costs for planned scrap in any level
- DOP alarms are not generated as long as reported scrap is less than the planned scrap
- DOP enhancements
- Possibility to net DOP orders directly from excess quantities available on shop and purchase orders
Possibility to re-prioritize a part quantity from one DOP order to another order by unreserving the temporary inventory - Possibility to deliver a quantity not required by a parent DOP order, or pegged customer order line to stock
- Possibility to unreceive/cancel receipt of a quantity delivered from a shop / purchase order to a DOP order without unreserving the quantity first
- Possible to use the same flow for handling purchase requisitions from DOP as other requisitions
Make it possible to follow traditional numbering system for DOP Orders. - Easier to keep track on DOP Orders and Shop Orders, especially when the amount of orders being handled are very high.
- DOP Lobby
- Provides a graphical high level view of the current ongoing DOP Orders
- Built-in focus on open items and highlights the most important things to do
- Easy personalization with filters for site, planner and project
- Perspectives to act on, to do and to deliver
- Drill-down from each element to detail information
hope this helps!
Ana