We have a part that is machined on any 1 of 8 different machines. Each machine is its own work center. Each work center is setup as a different alternate routing for the part. When CRP is calculated, load from shop order requisitions will only appear on the work center that’s on the primary routing. This machine/work center always appears overloaded, while the alternates appear to have plenty of capacity, even though the load will be spread across all machines.
Is it possible to generate load from shop order requisitions to alternate routings?
Thanks,
Eric