Skip to main content
Solved

Closing Audits with attached NCRs

  • January 18, 2022
  • 1 reply
  • 137 views

Forum|alt.badge.img+9

We use the audit functionality to perform production line audits.  NCRs are then created and connected to the audit.  Some of these NCRs require action others do not.  We would like to be able to close the audit independent of the NCR status.  The documentation I've found so far states this is possible, however, it's not allowing us to close the audit's without first closing the NCRs.  This is an issue for us because while the audit is complete, the NCR may need to remain open until the non conformity is corrected.

Can you please provide documentation on how to close audits with attached NCRs without having to close the NCRs first?

Regards,

Peshala.

Best answer by Peter Lundgren

Have you tested the different settings for the Open NCR Allowed column in the Audit Type basic data page?

 

This topic has been closed for replies.

1 reply

Peter Lundgren
Hero (Employee)
Forum|alt.badge.img+7
  • Hero (Employee)
  • 62 replies
  • Answer
  • January 18, 2022

Have you tested the different settings for the Open NCR Allowed column in the Audit Type basic data page?