Question

CBS - IFS scheduling

  • 23 March 2022
  • 3 replies
  • 181 views

Userlevel 5
Badge +7

Dear Sirs;

I use Interactive Scheduling Client on CBS APP10.

Please take a look at the picture below.
The date S2 and S3 is holiday. You can find 3 shop order plan across the holidays.
I hope that those shop orders is schedlued complete before the holiday.
Any idea to control those case??
 

 


e

Regards;
Yasuda


This topic has been closed for comments

3 replies

Userlevel 5
Badge +7

I’ve never have any response on this topic. This issue is still active with me. please help.

Userlevel 5
Badge +13

Did you try setting up these days as Schedule Exceptions and connected the exception to your manufacturing calendar? This would allow you to set these days as non-working days.

Userlevel 6
Badge +13

Hi @CheSusumY,

 

It is not quite accurate to determine whether your Shop Order is actually scheduled for a non-working day just by looking at the schedule line. Though it runs across non-working days the operations of it  could be actually loaded only on working days. 

For an example;

In the yellow marked area you can see the Calendar “TI-CAL1” does not have any working days, so there is nothing loaded for those 2 days (red circled area) in the work center “NS-W1”.
However, you can see that the schedule line of operation 211250-*-*-1 is running across, but that does not mean the operation is loaded for non-working days.

 

Let me know whether this clarifies your question.