Skip to main content
In App 10 testing one of the customer who I am working with, received following error message when trying to copy a project - the dates for the project are within the dates:



calendar * has not got enough working days in the period you want to copy the project to! Make sure the calendar is generated for the entire project period
This issue can occur if your Project Planned Finish date (and Activity end date) is a larger date than your Calendar End Date. Therefore, need to check project Planned Finish date, Activity End date and Calendar End date in your Issue having environment. Both Activity End date and Project planned Finish date Should have smaller dates than your Calendar End date. In addition to that, your calendar should be a Generated Calendar which can be identified in calendar status.

@Peshala Fernando  did you find your answer? 

we’re having this same issue and we verified our calendar end date is beyond and our planned finish date and the dates are set as working days - we have no activity tied to this nor a subproject. 


@ghaschke I have witnessed in some customer installations where Calendar ‘*’ does not function properly. One example is when used on a Work Center, capacity does not get calculated for the days in the ‘*’ calendar. Consider using a calendar that is built the same as the * calendar.


Reply