Hi, I have the following issue. Please assist
Issue: When a person is assigned to a Resource ID, that Resource ID should be retrieved when the employee charges time to an activity.
In App10 I find that this did not occur.
Steps:
1. Open Resource Group and verify that employee is assigned to the resource on the Person tab.
2. Open Project Time Registration screen and search for employee (in the relevant company ) - should retrieve.
3. Add a line on the Week tab for Activity Short Name (eg: CC002.B.20) select a Report Code - notice that Resource ID remains blank.
I can select a resource, but none populates. It should populate with the primary resource the employee is assigned to.
Page 1 / 1
Hi Dinidu,
It is possible to specify a value in the Resource Detail such that it will be fetched as the default for an employee in Project Time Registration.
In Resource Details for a Person-Resource (the person objects connected under resources) look in the tab Connections/Company, there is a column called Primary Parent Group and in this column it is possible to select the resource group which is used as default value in Project Time Registration.
It is possible to specify a value in the Resource Detail such that it will be fetched as the default for an employee in Project Time Registration.
In Resource Details for a Person-Resource (the person objects connected under resources) look in the tab Connections/Company, there is a column called Primary Parent Group and in this column it is possible to select the resource group which is used as default value in Project Time Registration.
Had the same problem: my analysis showed that in the resource detail of the person, an entry in tab connections, tab employee has to be made, too.