(Cloud) Is there a function where there is routing operations logic?
What we are seeing is when we run the Advanced Planning Board (ABP), is that our operations are not scheduling directly after each other once the previous operation is completed.
For example,
We have Tool T1473 that has 2 instances (1733 and 1744)
Our Routing is setup
10 (Prep)- Uses Tool T1473
20 (Mix) - Uses Tool T1473
30 (Cure) - Uses Tool T1473
40 (Remove supports)- Uses Tool T1473
50 (Test) - No Tool used
Work Center is all the same (expect 50) with 1 Resource

And what I’m seeing is that during scheduling, the tool jumps from one tool instance to another tool instance instead of keeping with the same instance. And then also it starts Op 40 days later after Op 30 is done.
Is there a way to fix this? In other systems I’ve used, I’m used to seeing something like “Absolute Start after previous operation”, or “Delay start after operation”
Or do we need to look at setting up the router differently? I was exploring the WC’s resources as an option and putting the tool name under the resources. I thought about condensing but with our operations we have equipment that look for those Operation Steps.