We have a need to schedule the first operation of a shop order as soon as possible, and secondary operations as late as possible. Is this achievable with advanced planning board?
Purpose is to utilize available machine capacity at op 10 and have accurate start dates for raw material planning, but backwards schedule remaining operations so orders are finished as late as possible.
Machine work centers (Op 10) are finite and finishing work centers are infinite.
Thanks,
Eric
IFS App 10