Hi
i am using Apps 10 and have put a 1 day shop order gap on an inventory part so MRP would schedule only 1 shop order requisition each day. (below)

As you can see from the image below it is still scheduling 4 different shop orders to start on the same day at the same time which is not possible for us to achieve.

When I go into the actual shop order i can see the Earliest start date on all for shop orders have a 1 day gap between them but all have the same finish date. We use backwards scheduling so I don't think MRP looks at the earliest start date?




Why is there not a shop order start date gap of 1 day between the shop order ? and how do i achieve what i am trying to implement?
regards
Jamie