I have a Resource Assigned to my Project Activity and the internal pricing setup is:
My Resource, PROJECT MANAGER, only has General Cost setup of $133.33.
When I report an hour using the DWTT1 report code, the Internal Cost of the Project Transaction is $133.33. This was a shock to me.
The priority, as I know it is:
Since I have a report code defined, I believe the system should be following Priority 4. Am I reading this wrong? Is it because I have the Resource Defined as % that it does not follow Priority 4 and follows Priority 6?
Does this make sense that the system does not recognize the Standard Internal Price if it is setup with a Report Code but with % as the Resource ID?
Patrick