With respect to what parameters Schedule Capacity is defined as  Infinite Capacity or Finite Capacity?

Best answer by Rasangi Tilakaratne

Hi Yasanthi,

I believe you are referring to Work Center Scheduled Capacity. If yes, then the Scheduled Capacity is based on selected Work Center Code, where the following help information is available. 

But if you are referring to Scheduled Capacity relating to any HR product flows, then can you please specify the relevant window?

Anyway,  if it’s relating to Work Center,  then you can contact a Manufacturing Consultant to get a better understanding of this Scheduled Capacity Functionality.    

 

 

Best Regards,

Rasangi

This topic has been closed for replies.

3 replies

Forum|alt.badge.img+9

Hi Yasanthi,

I believe you are referring to Work Center Scheduled Capacity. If yes, then the Scheduled Capacity is based on selected Work Center Code, where the following help information is available. 

But if you are referring to Scheduled Capacity relating to any HR product flows, then can you please specify the relevant window?

Anyway,  if it’s relating to Work Center,  then you can contact a Manufacturing Consultant to get a better understanding of this Scheduled Capacity Functionality.    

 

 

Best Regards,

Rasangi


Forum|alt.badge.img+10

@Rasangi Tilakaratne Many thanks for the detailed response. This question was raised by one of the users and I’ll get back with more information if needed. 


Forum|alt.badge.img+9

Sure Yasanthi :-)