Dear Community, 

 

We encounter an issue during the IFS Installation in our upgrade project:

We are upgrading from IFS 8 to 10 following steps are followed for the upgrade.
- Take backup of PROD (Oracle 11g)
- Import this export to the new App10 DB (Oracle 19c)
- Complete the DB upgrade and fix any SYS invalids.
- Run IFS Upgrade on the upgraded DB.

The issue is:

The process gets hanged on the step 'Component DOP is ready'.

 


A SELECT Statement as per the screenshot attached keeps on running for more than 15hrs and after this is complete, installer does not continue beyond this point.

There are no error logs created as well.

 

If you have any fresh ideas what we can investigate that would be really appreciate it. 

 

Thank you very much for any ideas or thoughts! 

Kind regards,

Balazs


 

This is the stuck query: 

DECLARE
    CURSOR get_prjrep_connections IS
    SELECT
        *
    FROM
        (
            SELECT
                pt.activity_seq                               activity_seq,
                'PTR'                                         proj_lu_name,
                pt.activity_seq                               keyref1,
                pt.company_id                                 keyref2,
                pt.currency_code                              keyref3,
                to_char(pt.account_date, 'YYYYMMDD')          keyref4,
                '*'                                           keyref5,
                '*'                                           keyref6,
                'TRUE'                                        system_ctrl_conn,
                activity_api.get_description(pt.activity_seq) object_description,
                fnd_session_api.get_fnd_user                  created_by,
                sysdate                                       date_created,
                sysdate                                       rowversion,
                pt.account_date                               last_transaction_date
            FROM
                project_transaction_tab  pt,
                prel_invoice_posting_tab pip,
                project_connection_tab   p
            WHERE
                    pt.project_transaction_seq = pip.project_transaction_seq
                AND pt.invoicability != '2'
                AND pip.posting_type IN ( 'PRJI1', 'PRJI2' )
                AND pip.prjrep_posting_status != 'ERROR'
                AND p.proj_lu_name = 'PTR'
                AND pt.activity_seq = p.activity_seq
                AND nvl(account_api.get_exclude_proj_followup(pt.company_id, pip.code_a),
                        'FALSE') = 'FALSE'
            GROUP BY
                pt.activity_seq,
                pt.company_id,
                pt.currency_code,
                pt.account_date
            UNION ALL
            SELECT
                pt.activity_seq                               activity_seq,
                'PT'                                          proj_lu_name,
                pt.activity_seq                               keyref1,
                pt.company_id                                 keyref2,
                to_char(pt.account_date, 'YYYYMMDD')          keyref3,
                '*'                                           keyref4,
                '*'                                           keyref5,
                '*'                                           keyref6,
                'TRUE'                                        system_ctrl_conn,
                activity_api.get_description(pt.activity_seq) object_description,
                fnd_session_api.get_fnd_user                  created_by,
                sysdate                                       date_created,
                sysdate                                       rowversion,
                pt.account_date                               last_transaction_date
            FROM
                project_transaction_tab   pt,
                project_trans_posting_tab ptp,
                project_connection_tab    p
            WHERE
                    pt.project_transaction_seq = ptp.project_transaction_seq
                AND p.proj_lu_name IN 'PT'
                AND pt.activity_seq = p.activity_seq
                AND ptp.prjrep_posting_status != 'ERROR'
                AND ptp.posting_type IN ( 'PRJT1', 'PRJT3', 'PRJC1', 'PRJC3', 'PRJT5' )
                AND pt.supp_invoice_id IS NULL
                AND pt.supp_invoice_no IS NULL
                AND pt.report_cost_type IN ( '1', '2' )
                AND ptp.company_id = pt.company_id
            GROUP BY
                pt.activity_seq,
                pt.company_id,
                pt.account_date
        ) prjrep
    WHERE
        NOT EXISTS (
            SELECT
                1
            FROM
                project_connection_tab pc
            WHERE
                    pc.activity_seq = prjrep.activity_seq
                AND pc.proj_lu_name IN ( 'PT', 'PTR' )
                AND pc.proj_lu_name = prjrep.proj_lu_name
                AND pc.keyref1 = to_char(prjrep.keyref1)
                AND pc.keyref2 = prjrep.keyref2
                AND pc.keyref3 = prjrep.keyref3
                AND pc.keyref4 = prjrep.keyref4
                AND pc.keyref5 = prjrep.keyref5
                AND pc.keyref6 = prjrep.keyref6
        );

    TYPE prjrec_connection_ IS
        TABLE OF get_prjrep_connections%rowtype INDEX BY BINARY_INTEGER;
    prjrec_connection_tab_ prjrec_connection_;
    bulk_limit_            NUMBER := 10000;
    start_time_stamp_      DATE;
    finish_time_stamp_     DATE;
BEGIN
    start_time_stamp_ := sysdate;
    OPEN get_prjrep_connections;
    LOOP
        FETCH get_prjrep_connections
        BULK COLLECT INTO prjrec_connection_tab_ LIMIT bulk_limit_;
        IF ( prjrec_connection_tab_.count <> 0 ) THEN
            FORALL i_ IN prjrec_connection_tab_.first..prjrec_connection_tab_.last
                INSERT INTO project_connection_tab (
                    activity_seq,
                    proj_lu_name,
                    keyref1,
                    keyref2,
                    keyref3,
                    keyref4,
                    keyref5,
                    keyref6,
                    connection_seq,
                    object_description,
                    system_ctrl_conn,
                    created_by,
                    date_created,
                    rowversion,
                    last_transaction_date
                ) VALUES (
                    prjrec_connection_tab_(i_).activity_seq,
                    prjrec_connection_tab_(i_).proj_lu_name,
                    prjrec_connection_tab_(i_).keyref1,
                    prjrec_connection_tab_(i_).keyref2,
                    prjrec_connection_tab_(i_).keyref3,
                    prjrec_connection_tab_(i_).keyref4,
                    prjrec_connection_tab_(i_).keyref5,
                    prjrec_connection_tab_(i_).keyref6,
                    project_connection_seq.NEXTVAL,
                    prjrec_connection_tab_(i_).object_description,
                    prjrec_connection_tab_(i_).system_ctrl_conn,
                    prjrec_connection_tab_(i_).created_by,
                    prjrec_connection_tab_(i_).date_created,
                    prjrec_connection_tab_(i_).rowversion,
                    prjrec_connection_tab_(i_).last_transaction_date
                );

            COMMIT;
        END IF;

        EXIT WHEN get_prjrep_connections%notfound;
    END LOOP;

    CLOSE get_prjrep_connections;
    finish_time_stamp_ := sysdate;
   --The following code is added to overcome the requirement to run a refresh after an upgrade (for apps10)
   --This will create connection details for the project connections without connection details
    project_conn_refresh_util_api.refresh_project_connection(start_time_stamp_ => start_time_stamp_, finish_time_stamp_ => finish_time_stamp_
    );
    COMMIT;
END;

Has this step of the upgrade process run before to compare how long it took to complete (or) is this your first time running the upgrade pass?

Can you check for any blocking locks inside the database?

If you don’t see any errors, please allow the upgrade (Main Install) step to complete. The upgrade process timing depends on a lot of factors including the size of database.
You can review this step to see whether there is room for improvement on the timing, by allocating more resources to the DB as per IFS recommendations during subsequent runs.

You can also provide feedback whilst sending upgrade logs for IFS to review.