Hello,
We are trying to test IFS Cloud Project Management features based on some of our large-scale project work for next year. I’ve created a 30,000 task project in Microsoft project and I’m trying to import it into IFS. If I keep trimming down the tasks of the project, I can eventually get it to import. It usually works somewhere below 1000 tasks. (Note: operations are not related to tasks.) Is there some kind of limit setting that we can adjust to get this to work?
Error: The current change set contains too many operations. Only change sets with a maximum number of ‘1000’ operations are allowed.
Does someone know where we might be missing a setting? Is it in IFS or MSProject?
Thank you,
Joann