Skip to main content
Solved

Calculate a Date Based on the Number of Workdays from a Given Date


Forum|alt.badge.img+4

I use the work_time_calendar_api.get_work_days_between() function in several of my SQL scripts, and it works great. Is there a way, using the work time calendar, to calculate a date from a given date with a delta?

For instance (pseudocode): get_work_days_between(calendar,‘2024-09-03’,’2024-09-05’) will return 2 in my environment.

Is there a function that exists that will allow a date argument ‘2024-09-03’ and a variable argument of ‘2’ and return the value of ‘2024-09-05’?

thanks!

Eric

Best answer by dsj

Hi @emiller3061 

 

I think Work_Time_Calendar_API.Get_End_Date(calendar_id_, start_date_, duration_); would get you the result.

 

/Damith

View original

dsj
Ultimate Hero (Partner)
Forum|alt.badge.img+22
  • Ultimate Hero (Partner)
  • September 5, 2024

Hi @emiller3061 

 

I think Work_Time_Calendar_API.Get_End_Date(calendar_id_, start_date_, duration_); would get you the result.

 

/Damith


Forum|alt.badge.img+4
  • Do Gooder (Customer)
  • September 5, 2024

Thank you!



Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings