Planned Revenue is not updated for the Customer Order Rental lines

  • November 11, 2025
  • 1 reply
  • 11 views

Forum|alt.badge.img

We’ve created a Customer Order that includes both regular order lines and rental lines, all of which are linked to the corresponding project and activity sequence. However, in the Project, the planned revenue is being updated only for the normal order lines, not for the rental lines.

Am I missing any specific setup for this?

Any guidance on this would be greatly appreciated.

1 reply

Marcel.Ausan
Ultimate Hero (Partner)
Forum|alt.badge.img+22
  • Ultimate Hero (Partner)
  • 1303 replies
  • November 11, 2025

@ArcMariGa pls check the background jobs. Normally there’s a job called Refresh project revenue for Customer Order Line which errors out if your PostinG Control for your Cost/Revenue code part is not setup.

Now, I’m not sure what posting controls are used for Rental events but if they are missing you’ll see that in the refresh job. See an example below: