IFS Apps 9 Projects - Posting Controls GP22 - GP25

  • 27 April 2021
  • 2 replies
  • 283 views

Userlevel 1
Badge +2

Can anyone help me with what transaction triggers the Posting Controls of GP22 - GP25?  I can’t get these transactions created in the application.  What process creates these?

icon

Best answer by BAKLarryG 28 April 2021, 05:21

View original

This topic has been closed for comments

2 replies

Userlevel 7
Badge +15

Hi @BAKLarryG,


 

GP22 is for Unbillable Project Revenue

GP23 is for Overbilled Project Revenue

GP24 is for Contra Account Unbilled Project Revenue

GP25 is for Contra Account Overbilled Project Revenue

 

With IFRS 15 there has been a requirement to recognize revenue for different milestones of a project.

With this requirement it was identified that for a construction type of a project, there can be different milestones/events to recognize revenue. Hence there should be the ability to define costs and revenue for different milestones of a project.

Therefore the solution was as below.


-New revenue recognition method ‘Event based’
-Possibility to define events and connect revenue, cost and percentage of completion (POC) to each event
-Revenue recognition based on amounts connected to events

In order to comply with this requirement in IFRS 15 of presenting the difference between actual and recognized revenue separately  in the Balance sheet a new development was done.

According to IFRS 15, we should compare the recognize revenue with  actual revenue and then the difference should be shown as a liability or asset. If the difference between recognize revenue  - capitalize revenue is a positive amount it should be treated as an asset. And if the difference between recognize revenue  - capitalize revenue is a negative amount it should be treated as a liability. 

Hence as a solution,


-A new checkbox "Post Actual and Recognized Revenue Difference" to decide separate postings for actual and recognized revenue difference
-New posting types to post the actual and recognized revenue difference (GP22, GP23, GP24 and GP25) separately in the Balance Sheet.



Hope the above information would be useful to you :relaxed:

Thanks & Best Regards,
Thanushi

Userlevel 1
Badge +2

Thanushi -

 

Thank you very much for this response.  When I change the Revenue Recognition method to Event Based, the text says that the user can define events with revenue and costs to recognize for each event.    

You mention it above as “Possibility to define events and connect revenue, cost and percentage of completion (POC) to each event”.   

What type of setup is needed for these events?   Where is this done?

Is it possible to still use POC Income First as the Rev Rec Method, and still  use the checkbox for “Post Actual and Recognized Revenue Difference?

 

Thank you again for your response