Underlying issue is that we can’t close a NAV project until all activities are completed.  This causes a problem because in our line of business, it could take up to a year for a customer to pay retention.  We don’t want to continue running Rev Rec on a project that is 100% POC and 100% billed.  We manage 100’s of projects and it muddies the reporting to have projects that are complete but being included in the Rev Rec reporting.  The only current work around I know of is to set the valid date of the FIN project to the future.  Not my favorite thing as there’s nothing to on the NAV project to indicate this status.  Anyone else with this kind of issue?  Any suggestions?  Has anyone done any customization?

Be the first to reply!