Hi everyone, does anyone have experience with scheduling tools or equipment? I understand that PSO currently can't handle this, but is there a way to plan or reserve a tool manually for carrying out a specific activity? 

Hi RUGGERO,

It sounds like the parts functionality in PSO may be what you are looking for. We support a wide range of features around parts, which allow parts to be consumed or reused and collected from depots. Have you checked out our documentation?

Scheduling Concepts - Parts.pdf

 

Any questions let me know,

Thanks,

Kai


Hi Kai

The issue seems to be that we don’t currently manage the scheduling of tools, which means we lack a clear overview of whether a tool is in use or reserved for a specific activity. As I understand it, the only way to address this right now is to treat the tools as resources and schedule them in the same way we do with technicians

thansks

Ruggero