Is it possible to create a UI specific customization in PSO which can be used to filter set of tasks & perform a bulk status change for the same. Ex : Allocated to Commited.

If Yes, can you please share the details accordingly. Thanks in advance.

How about filtering and then selecting multiple activities on the resource or activity Gantt by holding the Ctrl key? Then you will see the list and an edit button…

 

...that allows you to change the status.

 