Hi,

It is possible that PSO takes into account the stock of a resource before allocating the activity? Please take into account the fact that data comes from IFS Cloud, it is an integration between PSO and IFS Cloud (FSM). At the moment I do not see the ,,parts" tab on the resource, in PSO.

Thank you in advance!

Best Reagrds,

Miruna

Hi Miruna, parts are currently not supported by the IFS Cloud/PSO integration.


Hi @Alexander Heinze ,
do you know if this is currently in IFS roadmap?

Thank you


@Eleazar_AyaviriCarrillo , @Miruna M  I cannot give a precise answer, but for your planning: It’s not in the short-term roadmap, so don’t expect anything in the coming two releases.


Is there any update on when Parts are due to be integrated between IFS Cloud and PSO? 

With stand alone PSO the feature is very useful, and is long overdue for PSO with Cloud. Is this what is meant by “Parts Scheduling” in Mobile Workforce Management on the roadmap for “Next” e.g. sometime post 25R2?

 


@Björn Kleist FYI