On our ongoing solution/project we are using datasets to control the access within PSO, but with FSM6.13 there is a new table (PSO_OBJECTGROUP_ACTIVITY/RESOURCE) which integrates with PSO and should be used for this specific requirement.

We are planing to group all datasets we have (>30) into one single dataset.

 

My problem is that we have a lot of teams and the EXPORT_TASK_TEAMS Sched App Param is limited to 2000char!

How can we configure the system to sync all task/resource to this new dataset??...

I already tried with ‘*’, ‘%’, ‘ALL’, ‘’,  but none of these values worked.

 

 

Best regards,

Hi João,

I don’t believe it’s possible to use a wildcard unfortunately, it has to be a comma delimited list.

Kind Regards,

Tom