Assignment using Dispatch console

  • March 20, 2023
  • 0 replies
  • 82 views

Forum|alt.badge.img+11

I created a task & trying to assign to a resource directly from work task screen (not from dispatch console), then it allows me to change the allocated finish date irrespective of the allocated hrs

but when I assign this task from dispatch console, I cant change the allocated finish. It populates the date based on duration.

What is the reason? I actually want to use dispatch for assignments but need flexibility to change the allocated end date with the same hrs.