Question

IFS 10 WORK TASK AND WORK TASK STEPS

  • 20 October 2022
  • 1 reply
  • 187 views

Userlevel 1
Badge +2

WHAT'’S IS THE DIFFERENT BETWEEN WORK TASK AND WORK TASK STEPS IN IFS 10?

WHAT'S TIME REPORT IN IFS 10?

 


1 reply

Userlevel 6
Badge +10

Hi Patrick,

  • Work task is the planning object for a planned period of work for one or more persons, which is linked to a single work order. It defines the demands (resource, material etc.) to fulfil the requirement, collects cost and generates revenue. The activities are defined as task steps.
  • Work Task Steps are the details of steps that are required to perform a work task. The work task step is not a sub task, and the difference is that it is not possible to add demands (resources, materials etc) on a step line or to create transactions (time, issues etc.) directly to a step.
  • You can report the amount of time spent on a specific job and who did it in time reporting. I.e. reporting of actual costs which is done by reporting hours for Employees and Tools.

Hope this helps.

 

Best Regards,

Yasanthi

Reply