Question

Method to change structure status

  • 6 December 2022
  • 6 replies
  • 217 views

Badge +1

Hello,

I want to change the structure status from “tentative” to “buildable”. I am using a two step job and I am looking for the right method. I was trying with this one (screenshot), but I get the message that the method is not righT. could you please advise?

Thank you!

Aleksandra


6 replies

Userlevel 3
Badge +7

Hi Aleksandra,

I tried it and this worked. I assume its the fact that it should be UPPERCASE

 

PROD_STRUCT_ALTERNATE_API.BUILD__

 

R,

Koen

Badge +1

Hi Koen,

I tried your solution but I receive still errors.

I shared also my screen of SOURCE MAPPING and DATABASE INFORMATION maybe something is wrong there. Thank in advance for your help.

 

Kind regards

Kris

Badge

Hello, 

 

Sorry this is not a question about this topic but what is the name of tool (or sofware) that you use on the pictures ? 

Thank you.

Badge +1

Hello @jonathanBRUGERE,

It’s a IFS Cloud Aurena. We are using the method of 2 step migration by jobs.

 

Kind regards,

Userlevel 3
Badge +7

@jonathanBRUGERE  this is the data migration framework used within IFS to migrate data into IFS using for example CSV files. This for each entity within IFS 

Badge

Ok i understand, We use until now, the migration task in IFS but not IFS Cloud Aurena.

Thank you ,

 

 

Reply