I am just wondering if there is anything in IFS for handling a concession request from a supplier? I’ll give a typical example, supplier A says they machined quantity 1 of 3 components 0.05 mm too small and ask us can we accept. We review and say yes. We need to document this concession IFS so when the component arrives, the inspector is aware of the concession. If the inspector is not aware of it, he will only create a MRB unnecessarily.
Best answer by Lahiru Dissanayake