Dear Community Members,
after UPD26 in my IFS10 version EE we faced an issue with connecting parts with proper Supplier Agreement.
The case is:
We have a Supplier Agreement with Part Assortment in use - there are 3 nodes coming from current Assortment. Very general ones to cover all parts.

The process of prucurement starts in Purchase Requisition where Part No, Supplier, price, project connection are defined. Then we Release and Transform the line into PO. At that stage system does not recognize the PR Line as to be assigned to Supplier Agreement and in the created PO column for Agreement No is empty. We cannot choose the Agreement No manually eaither.
When the same process is performed for Supplier Agreement with Parts it is correct. Part No from PR Line is recognized as part included in Supplier Agreement and in the created PO the reference to proper Supplier Agreement no appears in Agreement No and Agreement Line.
When line in PO is added manually it is also recognized properly, but not always…

I will add that before UPD26 we did not use Part Assortment at all. System allowed to assign Agreement No in the created PO manually from the LoV for the parts not included in Supplier Agreement Part tab.
If you have any idea what might be wrong or how to solve it, please let me know.
Thanks in advance.
Karolina