I am wondering if there is a way to assign a single PR line to multiple activity sequences-for example, if I am ordering 10 of a certain part, can I assign 5 to one activity sequence and 5 to another without having to create multiple PR lines/PO’s? 

 

I am new to IFS but familiar with SAP, and I know that SAP has this functionality. 

 

Thank you!

icon

Best answer by jabous 5 May 2022, 20:49

View original

2 replies

Userlevel 7
Badge +15

Currently there is no way in the IFS Application to connect multiple project activities, to 1 purchase requisition line. You could enter your issue on the IFS Idea Wall, for R&D to review your request. 

Badge +2

I will do that, it is a really useful function. Thank you for the quick response!