Can you have the pre-posting selected within the project navigator so that it is pulled into the req when the requisition is created. Rather than having to assign every line the pre-posting individually - - a PO that will have 100 lines, this gets time consuming.
Page 1 / 1
Hi
Do you want to copy all Pre posting setup in the Project to your PR line created from the Demand tab?
If that is the requirement then it is possible.
- I have a Project with following Pre posting
- Setup posting control for M113.
- Create a demand line.
- Create a PR and see for Pre posting.
Is this what you expected?
Regards,
Kasun