Hello,
I’m looking for guidance on an issue I’m encountering with PMRP and the use of standard inventory.
I have a project configured to use standard inventory and to automatically generate MTRs. The parts involved are within their lead times, and I’ve confirmed that MTR creation should be possible. However, when I run PMRP by Activity for the entire project (leaving Activity Sequence blank), only one activity receives an MTR. The other three activities generate purchase requisitions instead—even though I know sufficient excess exists in standard inventory.
If I run PMRP on each activity individually, or if I use a Planned Netting Group, all activities generate the expected MTRs. This leads me to believe that when PMRP is executed for the full project, only the final activity processed is considered for standard inventory availability.
Has anyone experienced this behavior or know what configuration or process I might be overlooking?
Thank you.
Andrew