Master Schedule for Purchase Parts

  • September 10, 2025
  • 1 reply
  • 49 views

Forum|alt.badge.img

Hello, All, 

Master Schedule by Part form does not take into account Purchase Orders that are with past due dates, when calculating supply proposals. Is there a way to fix this? 

 

1 reply

Forum|alt.badge.img+14
  • Hero (Employee)
  • September 11, 2025

Hello,

Please open the Site page and checkout:

Unfortunately these settings affects the loading of supplies into Master Scheduling (MS). We are thinking about a solution where it only affects the ATP calculation within MS. Now you have to include Past Due Supplies.

*** Small update - you also need to set a value in Past Due Days. 30 days?

Cheers,

Mats