Hi Community,
Is there anything that can be implemented in IFS to prevent IPAP due dates being updated when a PO is registered as arrived?
When Pre-registering arrival/pre-receipt of order for P1079950, the Due date in IPAP shows as 31/12/2024 which is also reflected in the PO screen and is the correct due date, as the two images shown here
The action of registering an arrival of a raw material PO is somehow adding on false additional days (date of receipt (05/11/24) minus planned arrival date (13/10/24) that is 23 days) to the IPAP due date (31/12/2024 + 23 = 23/01/2025) which giving the buyers incorrect information when managing their stocks and ensuring they have raw material to meet demand.
But the PO screen still showing correct planned receipt date 31/12/2024.
Best regards,
Jason