Hello community! Our company is experiencing an issue and we are looking for some help from the team. When we run MRP, our purchase requisitions are being created with wanted delivery dates short of lead time if there is already a confirmed purchase req in existance that has not been received yet. IFS is assuming that we can simply consolidate these POs, even though the new demand does not give enough lead time. Is there a setting that will allow all new purchase reqs to create at lead time regardless of other open purchase reqs existing? EXAMPLE BELOW
Today is 6/3
Part has a 40 day lead time.
There is a purchase req already existing that was created on 5/19 that is due 6/28
New demand is introduced, mrp runs, and a new purchase req is created today (6/3) with a wanted delivery date of 6/28 instead of 7/13 (40 day lead time)
IFS is assuming that I can consolidate the POs, however, I am now only giving 25 days lead time for the new demand.
Is there a setting that is turned on that is causing this to happen? Why would the new PO not show a wanted delivery date of 7/13 (40 day lead time) instead?