Skip to main content
Solved

How to Cancel a no Part PO order line on a received change order

  • January 20, 2020
  • 2 replies
  • 609 views

lvesters
Do Gooder (Customer)
Forum|alt.badge.img+2

Hello -

 

I have a user that has a PO with a change order and all of the lines are closed except for 1. He would like to cancel this line due to supplier delay but cannot because the change order has “Received” status.

 

I am new to IFS and am unsure of how to advise him to cancel this last line due to the status of the change order.

 

Is this possible to do?

 

Many thanks!
Leslie

 

Best answer by PRODQ

Try creating another Change Order and then cancelling the PO line in the change order.  I think once you’ve created a Change Order against a PO, all subsequent changes have to be processed via a Change Order.  

 

 

2 replies

PRODQ
Superhero (Customer)
Forum|alt.badge.img+18
  • Superhero (Customer)
  • Answer
  • January 20, 2020

Try creating another Change Order and then cancelling the PO line in the change order.  I think once you’ve created a Change Order against a PO, all subsequent changes have to be processed via a Change Order.  

 

 


lvesters
Do Gooder (Customer)
Forum|alt.badge.img+2
  • Author
  • Do Gooder (Customer)
  • January 21, 2020

Thank you Linda!