Just looking for any “left of centre” ideas or suggestions, please…
We have demand for the same purchased part (same site) from
- Projects
- Projects with purchase req authorisation
- Customer Orders
- Shop Orders
- Material reqs
We run PMRP and MRP which generates the necessary reqs but we’re unable to consolidate the supply onto a single Purchase Order. You can mix Projects and non-project demand onto a single PO but once the req is a project one that needs purchase authorisation you can’t mix with any other POs…
Any ideas gratefully received..