maybe someone can clarify for what purpose the tab “Work Orders” is needed in the form “Isolation Order”?
Work orders there are attached only manually.
If Work Order is connected to Isolation Order via Permit, the information of such Work Order doesn’t appear in this tab. Such connection is seen only in the form “Work Orders, Permits and Isolation Orders”, but not on Isolation Order.
So I do not understand for what purpose this tab is needed in Isolation Order. Connections of Isolation Order and Work Orders that are made in this tab doesn’t apply any rules for Isolation Order and Work Orders dates too.
Best answer by Priyanka Kurukuladithya
Isolation procedure (establishment and reestablishment) may need a separate WO/s to plan resources/material if the procedure is complex. Such WO/s can be manually created and connected to the Isolation Order through this Work Order tab. When the Isolation Order is set to Verify Operability or Historical there is a check to see if this connected WO/s are done or not. But this will not raise and error but an information message only. I am not aware of any other usage with this. Instead of creating a separate WO for the Isolation, you can also add work tasks in the same work order connected to the permit.
Isolation procedure (establishment and reestablishment) may need a separate WO/s to plan resources/material if the procedure is complex. Such WO/s can be manually created and connected to the Isolation Order through this Work Order tab. When the Isolation Order is set to Verify Operability or Historical there is a check to see if this connected WO/s are done or not. But this will not raise and error but an information message only. I am not aware of any other usage with this. Instead of creating a separate WO for the Isolation, you can also add work tasks in the same work order connected to the permit.
Isolation procedure (establishment and reestablishment) may need a separate WO/s to plan resources/material if the procedure is complex. Such WO/s can be manually created and connected to the Isolation Order through this Work Order tab. When the Isolation Order is set to Verify Operability or Historical there is a check to see if this connected WO/s are done or not. But this will not raise and error but an information message only. I am not aware of any other usage with this. Instead of creating a separate WO for the Isolation, you can also add work tasks in the same work order connected to the permit.
Is there any standard possibility in IFS Cloud to connect permit to certain work task?