Hello,
I would like some help to understand how postings works for Service and maintenance module (IFS V8).
I need to use operations and time reports on work orders but the use of these functions create postings on which I have some issues. After authorizing postings, when I want to change WO status to Finished, I get an error message : " There is no project cost/revenue element to code part value ". I tried to Exclude from project follow-up the involved code part value but I had another issue when I changed WO status "Project Connections cannot be created for this account". I would like to know how to configure postings/accounts in order to finish work orders with operations and time report ? Is it required to set up a project cost/revenue element to use postings in Service and maintenance module ?
Also, I don't understand what is the link between work orders and project because in my tests I never linked work orders with project activities,
Regards,
Nicolas