Hello
In 25 R1, When a Work Order is linked to a Project Activity and a Work Task is cancelled while still having assigned resources and material lines, the associated committed costs continue to remain recorded against the Project Activity.
The key concern is that these costs are not automatically rolled back to reflect the cancellation of the Work Task.
Could someone clarify the recommended approach to correctly adjust or reverse these costs at the Project Activity level to ensure accurate project cost tracking? Alternatively, is this behavior considered a system defect/bug?
Your guidance would be greatly appreciated.
Thank You