Why are my zero dollar time transactions not transferring on work tasks.

 

Best answer by Thommy

@Cindyhutchins 

As of my understanding the 0 cost has never been transferred from Maintenance even in earlier releases where we just had Work Orders (and no Work Task).

This topic has been closed for replies.

3 replies

Osthewha
Sidekick (Customer)
Forum|alt.badge.img+8
  • Sidekick (Customer)
  • January 9, 2022

Hi, I have the similar problem. The time registration is missing resource  id, - and if the transaction has already been transfered, we are not able to correct them… and they also seem to block closing of the reporting period in Finance. Do you have that problem as well ?  Regards, Heidi


Cindyhutchins
Sidekick (Employee)
Forum|alt.badge.img+7
  • Author
  • Sidekick (Employee)
  • January 14, 2022

We not using the HR module or tracking time in IFS sorry.


Thommy
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • Answer
  • January 17, 2022

@Cindyhutchins 

As of my understanding the 0 cost has never been transferred from Maintenance even in earlier releases where we just had Work Orders (and no Work Task).