Hello everyone,

 

Can someone tell me if a route actions (calendar-based) that has been “not completed” in a work order can be plan again each day until she’s “completed“ in a work order or until its next occurence is generated ? (in IFS APP8)

 

Thank you for your help,

Regards,

Nicolas


This topic has been closed for comments

1 reply

Userlevel 5
Badge +12

Hi,

I can’t see that this will be possible to do in an automatic way.

The calendar plan is generated based on the maintenance plan setup and it is the next occurrence that triggers a new WO regardless if the route actions has been set to “not completed”.