I need some help understanding how Planned Finish Date and time is calculated on the Maintenance Plan of the PM Action. It seems like the system is only looking at the work list with the longest duration when calculating the Planned Finish Date. If I have a work list with duration of 4 hours, my Planned Finish Date will be 4 hours after my Planned Start Date, even though I have multiple operations with shorter durations on the PM Action. I have set up dependencies for all work lists (Finish to Start).
RMB on the line and select Jobs and Work Lists displays the correct date and time for each work list and the generated work orders also have the correct planned start and finish values.
Any suggestions on how to fix the Planned Finish date on the maintenance plan?