PM Action Due Date vs Actual Finish Date

  • October 8, 2021
  • 6 replies
  • 334 views

Forum|alt.badge.img+12

Is there a way of identifying the ‘Due Date’ of a completed PM Action?

 

Once a PM Action has the Work Order Generated and Closed, the Due Date is removed and the Planned Date updates to the Date the Work Order was prepared.

I need a way of knowing what Planned Date was so I can report ‘Required Maintenance in a Period’ vs ‘Completed Maintenance in a Period’.

 

How do I best achieve this? 

Best answer by Thommy

Tested on Update 11 and with Calendar based PM the Due Date stays.

But perhaps you have another setup then I test on.

Anyway, the only way forward as I see it is to make use of the dates on the work tasks created from the PM to do the ‘Required Maintenance in a Period’ vs ‘Completed Maintenance in a Period’. 

The other way would be to make use of the maintenance window Earliest Start -- Latest Finish and compare Last Work Task Completion Date (or Last Work Task Step Completion Date if you are merging PM’s) with that date window.

This topic has been closed for replies.

6 replies

Nethmini Kosvinna
Superhero (Partner)
Forum|alt.badge.img+18

Hi @lisa.gilesAB ,

What is the IFS application and the UPD you are using ?

 

Thanks ,

Nethmini


Thommy
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • October 11, 2021

Hi @lisa.gilesAB 

If you are using Application 10 the Due Date stays even after closing of the Work Order, so I assume that you are not using Application 10 but an earlier release.

Without testing it out in your version, I would think that you would need to go on the planned and actual dates on the Work Order to get what you want.


Forum|alt.badge.img+12
  • Author
  • Sidekick (Customer)
  • October 20, 2021

I am using IFS App 10. Once the Work Order has been generated the Due Date and Planned Date are clearing so I have no way of measuring when the Task should have been completed as I can no longer see that information? 

 

 


Thommy
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • October 20, 2021

What update are you running on?

What I could conclude was that the Due Date stayed in the version I did a quick test, but as you say the Planned Dates are cleared.


Forum|alt.badge.img+12
  • Author
  • Sidekick (Customer)
  • October 20, 2021

I am on Update 11


Thommy
Hero (Employee)
Forum|alt.badge.img+12
  • Hero (Employee)
  • Answer
  • October 20, 2021

Tested on Update 11 and with Calendar based PM the Due Date stays.

But perhaps you have another setup then I test on.

Anyway, the only way forward as I see it is to make use of the dates on the work tasks created from the PM to do the ‘Required Maintenance in a Period’ vs ‘Completed Maintenance in a Period’. 

The other way would be to make use of the maintenance window Earliest Start -- Latest Finish and compare Last Work Task Completion Date (or Last Work Task Step Completion Date if you are merging PM’s) with that date window.