Dear Community. 

I am working in 25R1 and previous versions, and have found when a Work Task Template has Material demand and the associated Maintenance Purchase Requisition is created from the Calendar Generation, it appears in the Currency of the Company, not the Currency as defined in the Supplier for Purchase Part record. 

The system does adjust the price on the PR to reflect the currency change, but still the PR appears in the incorrect currency, also, the default Tax Code on the Supplier for Purchase Part is not used. 

This requires us to continually review generated PR’s and PO’s to ensure they are in the correct currency with the correct Tax Codes, which seems silly since the default values are set on the Supplier for Purchase Part. 

Am I missing something here?

David.