Hi all,
I’m trying to understand the intended usage of Risk Analysis in IFS Cloud (as designed by IFS R&D), specifically in an Asset Management / Maintenance Work Order context.
Business requirement
In our maintenance execution process, a risk assessment is a mandatory step before work can start on a Work Order.
A typical example is working at height, where a risk assessment must be performed every time the job is executed.
Issue 1 – Risk Analysis cannot be created from the related object
From a user/process perspective, we need the flow to be:
-
Create Work Order
-
Create Risk Analysis from the Work Order (context-driven)
-
Complete + approve Risk Analysis
-
Only then allow Work Order execution to start
However, in IFS Cloud it seems Risk Analysis must be created first and only then linked to the Work Order afterwards.
This creates a usability and process problem, because the Work Order is the natural starting point and the risk analysis is an integrated step in the WO workflow.
Question:
👉 Is Risk Analysis intentionally designed to be created as a standalone object first, and not from Work Orders / connected objects?
If yes, what is the recommended best practice to enforce “Risk Analysis required before WO start” in IFS Cloud?