The quires relating to EV and Cost Progress.1)How is EV and Cost Progress calculate when Progress Method=Connected Objects?As we know EV=Planned Cost*Cost Progress.When Progress Method=Tasks the system works as expected.But when Progress Method=Connected Objects,as we change planned cost,the EV shows no impact but cost progress changed.Why cost progress change?2)How is EV and Cost Progress calculate when Progress Method=Connected Objects?3)Where should we set Top-Down/Bottom-Up Progress Methods on IFS?
Dear Experts,There is a requirement to copy sub project for a newly created project. When I perform copy sup project RMB on the newly created project node, I was getting the error below. However, I have correctly defined calendar as well. Appreciate if anyone support me to resolve this issue. Thank you.
Community, Project MTR cannot be used for materials that are moving from one site to another. is this statement true? Thank you.
Hello Team, Is there any possibility of adding a one-time deduction for “Application For Payment” in IFSAPP10?Using the deduction percentage option in sales contact will add the same deductions to every application created. Rather than that, is IFS have an option to add different deduction amounts to different AFPs made from the same contract? Then later same can be invoiced including deductions. Thank you..
Hi, We would like to use attachments in control plan templates, where the attachments of the control plan template are also copied into the created control plans (IFS10) However, that does not seem to work. We create a control plan template, add the attachments. But when we use that template to create new control plans, the attachments of the template are not attached to the newly created control plan. Is there something we do wrong, or is this not possible? If not, does anyone know a workaround besides manually adding the attachment to each newly created plan? thank you!
Looking to attach lines in a Purchase order in released status to a Project Activity. Is there any way to do this without re entering the purchase order?
We have a project that was created in Error and approved. Is there a way to delete both the project under project Management and also under financial projects? Thanks for your help. Bob Booth
For an Apps9 customer, I have observed that when creating MCPR invoices the ‘Multi-Company Project Invoice No’ is not updated correctly in the customer transactions.1. Create MCPR transactions > Approve from both companies > Create the preliminary invoice from Employee company2. “Multi-Company Project Invoice No” field is updated correctly in Customer company transactions.3. Release the Preliminary invoice > Then final (PJ) invoice will be created4. ‘Employee Project Transactions’ > Note Invoice No is updated correctly5. Go to Customer Project transaction > ‘Multi-Company Project Invoice No’ is not updated correctly. Any reason for this?Thank you
Hi, Trying to credit Project Invoices - which are not the last generated and getting the below error message. Does anyone know about this or experienced it before?We are on application 20 and crediting application 16. Thansk, Matt
Hi, We are global company, and start using APP10 to set up multiple company reporting. We need knowledge on this. we have bunches of engineers from Canada are working on a Belgium project. They are trying to use the Belgium report code to do the time reporting, but not be able to. We know that could be resolved by MCPR setup, your step-by-step documentation is very much appreciated. Thank you.
The Task completion checkbox must be unchecked or Progress set to 0% before the Activity can be set to Canceled. The Task will then be deleted and there are no track on actually performed tasks on the canceled activity.The core functionality of deleting tasks is more suitable for Deleting a Project Activity than cancel of an activity when looking at an option to cancel a started activity. Test Scenarios:1. Create a project activity, set to status approved2. add a task with checkbox Completed set on the activity3. add a task with a progress between 0% and 100% on the activity4. Change status on the activity to Canceled (RMB/Status from the activity head)5. Verify, not possible to cancel activity due to task progress >0%-> Need to change task progress to 0% before Activity can be canceled and then all tasks are deleted -> No track on already performed work. Should It be possible to cancel an activity where you have reported progress on tasks ?
Already have an account? Login
No account yet? Create an account
Enter your username or e-mail address. We'll send you an e-mail with instructions to reset your password.
Sorry, we're still checking this file's contents to make sure it's safe to download. Please try again in a few minutes.
Sorry, our virus scanner detected that this file isn't safe to download.