Yes they are
seems the PO was created and then connected to the project!do you know the process of how the PO’s are being created? if this is the case you are never going to have planned cost. you can still close the project if all the transactions related with the PO are closed.
RMB on the demand line ( Update or retrive planned cost option) to obtain the planned cost On this case you need to have a look on the process of creating the PO was, I can suspect you created the PO without an expectd price and then the price was added later on the process of the PR or PO creation
Some PO shows that because they have some cost associated with it, in other cases , supplier for Purchase price may not exist hence planned cost is 0 The planned cost driver option is below what is the error message you are getting when trying to close the project? are you uing generate unifinsh activity work item option? to be able to close the project you need not to have inventory on the project and all invoicing completed
The employees are connected to another resource groups
thanks Johan, it does clarify , However, this differs of IFS project reporting documentation where the time is booked on the employee company, rather than on the customer company 🤷🏻
Thanks Johan, I had some play around it but I really strugle to undersatdn the funtionality on this , if you create a rule , you still have to input the customer activity detail when booking time and expenses… not sure what the aim is with the rules. Thanks,
Thanks Johan, from you answer could I conclude that this setting “Snapshot matching” is to change the snapshot after the forecast is created, because when I create the forecast , what is driving the calculation of the ETC /EAC seems to be the following setting”set ETC option” even if I change the settings of the snapshot matching - The calculation seems driven by the setting below. Thanks,
Very helpful. Thanks.
did you manage to get this sorted? I am interested on how the project deliverable structure should be updated to not duplicate items
the highest level can be defined as Phantom part, then have an item structure for each unit .
Already have an account? Login
No account yet? Create an account
Enter your username or e-mail address. We'll send you an e-mail with instructions to reset your password.
Sorry, we're still checking this file's contents to make sure it's safe to download. Please try again in a few minutes.
Sorry, our virus scanner detected that this file isn't safe to download.