Hi All,Good Day.Anyone has an Integration Procurement (ShipServ) Regression testing scenarios and test cases?Process is: RFQ (ShipServ) - Quote (IFS) and PO (ShipServ) - CO (IFS). Regards,VC
Hi All, Below is the error I am getting in Background Job. Any idea? ‘Error snapshot MRP Supply/Demand. MRP can not find required date of Order No 40108293 for Site/Part/ABC Class BCN/02200069821-C in calendar DIST’
Hi, Can anyone assist on letting me know how to enable ‘Email order’ available on PO header RMB. Regards.
Hello Folks, Would it be possible to utilize the external file assistant to upload count results into the Count Per Count Report screens? If yes, what will be the set ups and all. Regards.
Hi IFS Folks, Good day. I am wondering what is the difference between manual pricing and costing pricing in ‘Update Customer Agreements from Base Prices screen’. When I am using costing pricing it runs background job to update prices but there are no updated done but when I use Manual Pricing it works as intended. Please can anyone explain me the difference. Many thanks.
Hello,We’ve had an issue a few times now where the original customer order for a part was canceled , but no and since it was not informed, so the product was still reserved and shipped. There is no IFS stop on it until they go to deliver the order on the ‘Register Direct Delivery’ page, that there is an error.Can we automate the process of when an order line gets cancelled it also is cancelled on any connected purchase orders and customer orders? This process update would be specific to the intercompany orders between the two sites and the that sourcing option of primary supplier internal direct.
Hi – can anyone tell me if MRP will trigger purchase requisitions for status 5 parts that are showing inventory below safety stock?
Hi Folks, Need your guidance here:Is there an option in IFS to not change the price on a line item if quantity is changed? We have a situation where an order line is entered with a certain price. The order takes a long time to fill and then the system reflects the new price when they try to change the quantity since now the price in IFS for that part has changed. I would like to know if there is a way to “lock” the price on a line item. Thanks.
Hi Guys, Can anyone assist me on below error while trying to convert Sales quotation to Customer order getting error: Regards,Vaishali
Hi Guys, I have a doubt, when I am trying to release PO, it prompts me to add Pre Posting in Po line and then I can add and release PO but when I create Change order preposting prompts does not occur as they dont have that setup there and niether the new PO line added through change order prompts for pre posting and allows to release PO contrary to previous one.Your ideas!
Hi Members, I have a doubt here:A part has a stocking unit of measure of “EACH”. A case is made up of 12 each. Scene 1: Customer ABC orders 4 eaches, and the order is shipped for 4 eaches. Scene 2: Customer XYZ orders 1 case and the order is shipped for 1 full case. In this situation, the system should ship a complete case and not split it into eaches. Is this possible? How do the parts need to be setup? Is there additional setup need for parts like unit of measure etc.
Hi, I have a doubt here:A part has a stocking unit of measure of “EACH”. A case is made up of 12 each. Scene 1: Customer ABC orders 4 eaches, and the order is shipped for 4 eaches. Scene 2: Customer XYZ orders 1 case and the order is shipped for 1 full case. In this situation, the system should ship a complete case and not split it into eaches. Is this possible? How do the parts need to be setup? Is there additional setup need for parts like unit of measure etc.
Already have an account? Login
No account yet? Create an account
Enter your username or e-mail address. We'll send you an e-mail with instructions to reset your password.
Sorry, we're still checking this file's contents to make sure it's safe to download. Please try again in a few minutes.
Sorry, our virus scanner detected that this file isn't safe to download.