Hi Community,actually i fight lwith IFS Support and got this answer :====================== Start of fragment =================================== would like to reiterate what we mentioned before : “MS will never create any supplies inside PTF, that’s the idea with PTF. To create a stable production situation. This means they will not get supplies matching the demand dates inside PTF.”A couple of points to make :>> We have tested this in various Cloud versions, including 24R1 and application works as expected. Hence, you will not get any supplies generated within the dates you mentioned before====================== end of fragment ===================================This destroys all my assumed knowledge about IFS Master Scheduling.In general- DTF -> corresponds to a frozen zone, no change in demand and supply- PTF -> planning period, here supplies are created for the forecast recorded in the period in the form of shop order requisition, with certain parameters also over the
Hi, Have you encountered the following situation ?After scheduling with APB, the shop order start date is update accordingly. However, after 1 day, the date goes back to the initial shop order start date, without being rescheduled. What might be the issue behind it? Thanks!
Is it possible in finitely limited resources to firm/fix up shop orders and or operations so that APB plans around the firmed operations without moving the firmed/fixed ones? And if not, is there a workaround here
I know we can calculate demonstrated capacity for a single work center. Can demonstrated capacity be calculated for all work centers in a site? We have 100+ work centers and want to be able to compare demonstrated vs average capacity on a weekly basis without having to calculate each work center individually. IFSAPP10Thanks, Eric
Hello,Out of all our parts we have many that are “Planned by MS” and many that are “Site MRP”. I have found 4 parts (3 are in the structure of one) which are defined as “Selective MRP”. How would these have been set as “Selective MRP”? Does it result in any difference when MRP is run?Thank you.Regards,Basil
Hi, Does anyone know, whether scanner is supported to change the tracking structure in Shop Floor Workbench, tab Tracked Structure.IFS standard in APP10, RMB function support user to remove the current tracked structure, and if it is a touch screen, you could drag and drop the serialized part under the parent part, and rebuild the tracked structure. Instead of reading serials in visual, does system support scan the parent part, then the component serial no, then tracked structure is established immediately.Thank you.Ron
Already have an account? Login
No account yet? Create an account
Enter your username or e-mail address. We'll send you an e-mail with instructions to reset your password.
Sorry, we're still checking this file's contents to make sure it's safe to download. Please try again in a few minutes.
Sorry, our virus scanner detected that this file isn't safe to download.